P/087/2017 - Sri Manoj V.J | ||||||||||||
The consumer is aggrieved by the fact that the respondent had served a notice to the appellant directing to merge the connections to a single connection as both connections are using for the same purpose of lodging. If both connections are merged into a single one, the existing single phase is to be converted to a three phase for which huge amount is required. The appellant is liable to bear the expenditure for the conversion of his single phase connection to three phase. The cost of weather proof portion of the single phase service connection effected on 18-06-2016 for consumer number 10631 shall be deducted from the estimate cost of the present three phase connection. |
|
|||||||||||
KERALA ELECTRICITY OMBUDSMAN
D.H. Road & Foreshore Road Junction,
Near Gandhi Square,
Ernakulam, Kerala-682 016
Ph: 0484 2346488, Mob: 8714356488
Send an email to info@keralaeo.org
Today | 1319 | |
All | 5599067 |
P/063/2024, Sri. Rajendran .K |
03-01-2025 |
P/064/2024, Sri. Joe.I. Mangaly |
03-01-2025 |
P/082/2024, ശ്രീ.റിയാസ്.ഇ.ആർ |
03-01-2025 |
P/070/2024, ശ്രീ.സ്മിനോജ്.എം.എസ് |
03-01-2025 |
P/069/2024, ശ്രീ.അബ്ദുൾ കരിം സഹറുദ്ദീൻ P.M. |
03-01-2025 |
P/068/2024, ശ്രീമതി.സുകുമാരി.പി |
03-01-2025 |
P/065/2024, ശ്രീമതി. ജോസ്ന കെ.ജെ |
03-01-2025 |
RP/08/2024, Sri. Sunil Thomas |
04-12-2024 |
P/067/2024, Sri. Arun. C |
04-12-2024 |
P/066/2024, Sri. Shajan . N.P |
04-12-2024 |