NO.P/066/2014 - P. Sriram, Ernakulam | ||||||||||||
The appellant is the Project Director of Kochi Metro Rail Project of Delhi Metro Rail Corporation (DMRC). Their office is having power supply connection with consumer No. 23822 under Electrical Section, Girinagar. According to the appellant, DMRC is a public sector undertaking and electricity is not used for any construction purpose in the office. On 06-04-2013, the appellant submitted an application to change tariff from LT VII A to LT VI B. In spite of repeated requests, the tariff was not changed. Hence the appellant approached the CGRF on 18-06-2014 seeking to change tariff from LT VII A to LT VI B. The Forum, after hearing both parties, held that tariff of LT VII A allotted to the office of the DMRC was in order. Aggrieved against the said order, this appeal petition was filed. The respondent is directed to revise the tariff from LT VII A to LT VI B within a period of two weeks. Due credit may be given to the payments already effected. |
|
|||||||||||
KERALA ELECTRICITY OMBUDSMAN
D.H. Road & Foreshore Road Junction,
Near Gandhi Square,
Ernakulam, Kerala-682 016
Ph: 0484 2346488, Mob: 8714356488
Send an email to info@keralaeo.org
Today | 6159 | |
All | 5579892 |
P/063/2024, Sri. Rajendran .K |
03-01-2025 |
P/064/2024, Sri. Joe.I. Mangaly |
03-01-2025 |
P/082/2024, ശ്രീ.റിയാസ്.ഇ.ആർ |
03-01-2025 |
P/070/2024, ശ്രീ.സ്മിനോജ്.എം.എസ് |
03-01-2025 |
P/069/2024, ശ്രീ.അബ്ദുൾ കരിം സഹറുദ്ദീൻ P.M. |
03-01-2025 |
P/068/2024, ശ്രീമതി.സുകുമാരി.പി |
03-01-2025 |
P/065/2024, ശ്രീമതി. ജോസ്ന കെ.ജെ |
03-01-2025 |
RP/08/2024, Sri. Sunil Thomas |
04-12-2024 |
P/067/2024, Sri. Arun. C |
04-12-2024 |
P/066/2024, Sri. Shajan . N.P |
04-12-2024 |