Back assessment during meter faulty period – dispute on bill issued by the respondent – P/219/2011 – Shaju K.C., Manager, M/s Chemmannur Fashion Jewellery, Kozhokode.Back assessment during meter faulty period – disput . | ||||||||||||
The appellant challenges the meter faultiness and contended that the A/C unit became faulty and since the process of renovating the first floor was going on, resulted in the comparatively lower meter reading and consumption. The appeal was disallowed and confirmed the decision of CGRF. |
|
|||||||||||
KERALA ELECTRICITY OMBUDSMAN
D.H. Road & Foreshore Road Junction,
Near Gandhi Square,
Ernakulam, Kerala-682 016
Ph: 0484 2346488, Mob: 8714356488
Send an email to info@keralaeo.org
Today | 6522 | |
All | 5095481 |
P/047/2024, The Headmaster, Govt.U.P.School, Nadutheri, Pathanapuram |
03-09-2024 |
P/044/2024, The Secretary, Skyline Oasis Villa Owners Association |
03-09-2024 |
P/043/2024, Shri.Sarathchandran.M.S |
03-09-2024 |
P/041/2024, Shri.Jose.P.J |
03-09-2024 |
P/037/2024, Shri.Louis George |
03-09-2024 |
P/36/2024, Shri. Gopakumar.R |
03-09-2024 |
P/35/2024. Shri. K.N.Vijayan |
03-09-2024 |
P/034/2024, Shri. P.A.Paulose |
03-09-2024 |
P/033/2024 Shri.Joe Francis |
03-09-2024 |
P/032/2024, Sri.Naushad. A.R |
03-09-2024 |