KERALA ELECTRICITY OMBUDSMAN
D.H. Road & Foreshore Road Junction,
Near Gandhi Square,
Ernakulam, Kerala-682 016
Ph: 0484 2346488, Mob: 8714356488
![]() |
![]() |
![]() |
![]() |
Download details |
![]() ![]() |
||||||||||||
The appellant is the owner of a High Rise building having a HT electric connection with a contract demand of 70 KVA. The connection was given after installing a 150 KVA indoor transformer. Seven numbers of other LT connections were also given to the said building (from KSEB T’rfr) on the basis of the applications of the owner/rent holders or occupants prior to HT service with in a total of 50 KVA. While so, the appellant had applied for additional load for a LT connection. Since the total load of all the LT connections so availed in the building including the additional load requested) exceeds 50 KVA, the appellant was asked to install a separate transformer in his building premises, by the KSEB. Hence this dispute. |
|
|||||||||||
KERALA ELECTRICITY OMBUDSMAN
D.H. Road & Foreshore Road Junction,
Near Gandhi Square,
Ernakulam, Kerala-682 016
Ph: 0484 2346488, Mob: 8714356488
Send an email to info@keralaeo.org
![]() | Today | 5673 |
![]() | All | 6462355 |
P/018/2025, Dr, Zachariah Paul |
09-06-2025 |
RP/02/2025, Sri. James Kutty Thomas |
09-06-2025 |
RP/01/2025, Sri. Mohammed Ibrahim.K |
09-06-2025 |
P/026/2025, Sri.N.V.Jose |
09-06-2025 |
P023/2025, Sri.Surendran Chirakkal |
09-06-2025 |
P/016/2025, Smt. Ambily Vasudevan |
09-06-2025 |
P/024/2025, Sri.Jijo.T.A |
09-06-2025 |
P/019/2025, Sri. Vijayan .M |
09-06-2025 |
P/025/2025, Sri.Mohandas.K.K |
09-06-2025 |
P/022/2025, Smt. Mareena George |
09-06-2025 |