P-008-2022- Secretary, Royal Gardens, Ernakulamn-Order 21-04-2022
The APTS of the Licensee conducted an inspection in the premises on 09-07-2021 and detected that, even though the Current Transformer (CTs) used in the metering system was 200/5 ratio, Multiplication Factor used for arriving at the actual consumption is only ‘20’ instead of ‘40’. The inspecting officers of the Licensee prepared a site mahazar to that effect and issued a short assessment bill for Rs.23,79,177/- dated 29-07-2021 for the period from 14-04-2007 to 09-07-2021. The appellant filed a complaint before the Licensee, but rejected and hence, filed a petition before CGRF, Central Region and the Forum in its order dismissed the petition. Aggrieved by the decision of the Forum, the appellant filed appeal petition before this Authority. It is decided to quash the short assessment bill for Rs.23,79,177/- dated 29-07-2021 issued to the appellant. The respondent is directed to revise the bill period for twenty-four months prior to the date of inspection and issue within 15 days from the date of order. The respondent shall grant 12 numbers instalments without interest to the revised bill amount so prepared. The appeal petition filed by the appellant is disposed of as such. The order of CGRF, Central Region in OP No. 26/2021-22 dated 23-12-2021 is set aside.

Data

Size 150.74 KB
Downloads 620
Created 2022-05-17 06:30:50

Download

Contact Us

KERALA ELECTRICITY OMBUDSMAN
D.H. Road & Foreshore Road Junction,
Near Gandhi Square,
Ernakulam, Kerala-682 016
Ph: 0484 2346488, Mob: 8714356488

Any Queries?

Send an email to info@keralaeo.org

Do you Know?

Consumers should submit  petitions to CGRF first before appealing Ombudsman.

Visitors Counter

mod_vvisit_counterToday6837
mod_vvisit_counterAll5517072