The Petition filed by the appellant seeking to pass an order directing the respondent to remove the cross bars and overhead 1IKV electric transmission lines and other lines from the property of the appellant within a time bound manner. It is because of the visible infringement of electric transmission lines and cross bars encroached into the property of the appellant. The respondent is directed to initiate suitable action to remove the lines and cross arms from the property of the appellant by doing suitable rearrangement of 11 KV and LT cross arms or by shifting the ‘A’ type single steel pole in the same side of the road or by constructing a double pole structure in the same side of the road. The respondent can opt any of the suggestions, which is more economical and more technically feasible without obstructing the movements of vehicles and people through the roads. The expenses for the said work shall be met by the Licensee. The order of CGRF dated 30-09-2020 in OP No.14/2020-21 is set aside. |
|
|||||||||||
KERALA ELECTRICITY OMBUDSMAN
D.H. Road & Foreshore Road Junction,
Near Gandhi Square,
Ernakulam, Kerala-682 016
Ph: 0484 2346488, Mob: 8714356488
Send an email to info@keralaeo.org
Today | 3304 | |
All | 5583415 |
P/063/2024, Sri. Rajendran .K |
03-01-2025 |
P/064/2024, Sri. Joe.I. Mangaly |
03-01-2025 |
P/082/2024, ശ്രീ.റിയാസ്.ഇ.ആർ |
03-01-2025 |
P/070/2024, ശ്രീ.സ്മിനോജ്.എം.എസ് |
03-01-2025 |
P/069/2024, ശ്രീ.അബ്ദുൾ കരിം സഹറുദ്ദീൻ P.M. |
03-01-2025 |
P/068/2024, ശ്രീമതി.സുകുമാരി.പി |
03-01-2025 |
P/065/2024, ശ്രീമതി. ജോസ്ന കെ.ജെ |
03-01-2025 |
RP/08/2024, Sri. Sunil Thomas |
04-12-2024 |
P/067/2024, Sri. Arun. C |
04-12-2024 |
P/066/2024, Sri. Shajan . N.P |
04-12-2024 |