On 14-09-2021, the Anti-Power Theft Squad (APTS), Alappuzha team along with Sub Engineer of Licensee inspected the premises in the presence of the representative of the appellant and found that the ‘R’ phase of the meter was recording electricity below 29.7% of the actual consumption. A site mahazar was prepared in presence of the representative of the appellant. The appellant was issued a short assessment bill for Rs.96,147/- for the period from 03-07-2021 to 14-09-2021. The appellant challenged the bill before the CGRF, Central Region, Ernakulam and the Forum ordered to reassess the short assessment by revising the bills of 07/2021 and 08/2021 based on the average consumption computed from the three billing cycles after the replacement of the phase wire i.e., from 10/2021. The appellant filed the appeal petition to this Authority. Following decision is taken: (1) The appellant is liable to pay the bill as per short assessment arrived as per the decision of CGRF (Central Region), Ernakulam vide OP No. 53/2021-22 dated 03-03-2022. |
|
|||||||||||
KERALA ELECTRICITY OMBUDSMAN
D.H. Road & Foreshore Road Junction,
Near Gandhi Square,
Ernakulam, Kerala-682 016
Ph: 0484 2346488, Mob: 8714356488
Send an email to info@keralaeo.org
Today | 46 | |
All | 5517146 |
RP/08/2024, Sri. Sunil Thomas |
04-12-2024 |
P/067/2024, Sri. Arun. C |
04-12-2024 |
P/066/2024, Sri. Shajan . N.P |
04-12-2024 |
P/062/2024, ശ്രീ. മുഹമ്മദ് ഇബ്രാഹിം |
04-12-2024 |
P/061/2024, Sri. Mamathukutty |
04-12-2024 |
P/060/2024, ശ്രീമതി. ചന്ദ്രലേഖ & ശ്രീ .വി.എൻ ശശീന്ദ്രൻ |
04-12-2024 |
P/059/2024, Sri. M. Mohammed Haji |
04-12-2024 |
P/058/2024, Shri.P.N.Krishnadas |
04-12-2024 |
P/057/2024, ശ്രീമതി .നബീസ അമ്പലവൻ |
04-12-2024 |
P/056/2024, ശ്രീമതി. അജിത.കെ.വി |
04-12-2024 |