Demand of the consumer to install the meter at his house (at the end of the UG Cable) for his UG cable electric service connection- P/327/2012 – Rahmath Beevi, Kottayam. |
|
The appellant has applied for conversion of her existing 1- phase UG Cable electric service connection to three phase UG connection. It was directed the consumer to shift the position of the meter from the existing place (at the wall of house) to the beginning of the cable i.e. at the boundary of the premises or near the gate of the premises of the consumer. Held that the consumer is bound to act as per the prevailing regulations, as there exists specific rule to provide such UG connections. |
Misuse of electricity by tapping from one electric connection to another, both owned by the same consumer - P/331/2012 – Mymoona Khader Kunju, Oachira. |
|
The grievance has arisen out of the detection of extension of wire from one premise to another and the charges levelled against the consumer is under section 135 and the penal assessment made is under section 126 of the Electricity Act 2003. Complaints pertaining to the said sections are not maintainable before the CGRF and Electricity Ombudsman, as per clause 2 91)(f)9vii)(1) (CGRF & Electricity Ombudsman) Regulations, 2005. Petition remanded to the AE, the assessing officer to review the case and decide afresh as per law. |
Dispute on energy consumption during the Meter faulty period and reassessment bill issued – P/334/2013 – John BoscoC.J., Kochi. |
|
The KSEB has not taken regular meter reading of the consumer for a long period stating door locked position. The consumer was issued with an arrear bill for the disputed period. The consumer was paying only the minimum charges (fixed charges) for the whole disputed period. The consumer is bound to pay the charges of electricity he has actually consumed. Held that the reassessment period shall be limited to one year instead of 24 months.The loss to the Board on this account may be recovered from the concerned Board officials, responsible for the lapses on their side, to take the meter readings in time. |
KERALA ELECTRICITY OMBUDSMAN
D.H. Road & Foreshore Road Junction,
Near Gandhi Square,
Ernakulam, Kerala-682 016
Ph: 0484 2346488, Mob: 8714356488
Send an email to info@keralaeo.org
Today | 3450 | |
All | 5365011 |
P/055/2024, Shri.Mujeeb.M |
04-11-2024 |
P/054/2024, Shri.Sunil Kumar |
04-11-2024 |
P0/51/2024, Shri. Joy Joseph |
04-11-2024 |
P/049/2024, Sri. Roy Joseph |
04-11-2024 |
P/052/2024, Shri. Sunil Thomas |
04-11-2024 |
P/053/2024, Shri. K.M Raveendran |
04-11-2024 |
P/050/2024, Shri.G.Isaac |
04-11-2024 |
P/048/2024, Shri.David Saj Mathew & Smt. Aparna M.Babu |
04-11-2024 |
P/030/2024, Shri. Dr. Biju Ramesh |
03-10-2024 |
P/046/2024, Shri. Biji Sony |
03-10-2024 |