Downloads
Overview Search Downloads Submit file Up
Category: Orders
Order by: Default | Name | Date | Hits | [Descending]
Orders Files: 1280
Orders of Kerala Electricity Ombudsman  in pdf format
Files:
P/078/2017 Sri. Tomy C. Vadayil Kottayam

Download 
Download

The appellant, Sri Tomy C. Vadayil, M/s Toms Pipes, is an industrial consumer with No. 14329 of Electrical Section, Thengana. The consumer had applied for enhancement of his ‘connected load’ from111 kW to 155 kW and to reduce contract demand from 123 kVA to 99 kVA on 13-01-2017. But his request was denied by the respondent for the reason that the increase in connected load above 150 kVA is not possible under an LT service connection. Being aggrieved with the said decision, the consumer filed petition before the CGRF, Kottarakkara, on 06-02-2017. The CGRF dismissed the Petition on the ground that a consumer cannot claim to be retained as a LT service connection, when his ‘connected load’ has crossed the limit of 100 kVA (up to 150 kVA allowed to those as on the date of implementation of Electricity Supply Code, 2005) and hence found the petition devoid of merits. Here, the consumer has demanded his connected load to be increased to 155 kW, but at the same time he promises to limit his maximum demand (use of electricity) with in ‘contract demand’ of 99 kVA itself. Still aggrieved by the decision of CGRF vide order No. OP No. 361/2017 dated 19-06-2017, the appellant has filed the Appeal petition before this Forum on 10-07-2017. From the analysis done and the Findings and conclusions arrived at, I take the following decision. The consumer may either change over to HT category, if he requires 155 kW load or continue in the present connected load under LT category. He shall remove the excess load and may give application in Annexure 11 for reduction in contract demand, if he so desires. Having decided as above, it is ordered accordingly. The appeal Petition filed by the appellant vide appeal petition No. P/078/2017 is disposed of with the said directions issued. No order on costs.
P/073/2017 Sri. Mambram Divakaran, Kannur.

Download 
Download

The appellant is a Low Tension consumer bearing consumer number 9197 under Electrical Section, Pinarayi, Kannur District. The tariff assigned to this connection is LT VI F and the sanctioned connected load in the premises is 18340 Watts. The appellant had applied for additional connected load of 56 kW for the newly constructed floors of the four storeyed building having the height of 16 metres. The respondent has directed the appellant to construct the internal distribution network, including the service line, transformer, switch gear etc at his cost. So the appellant had approached the Hon’ble CGRF (NR) by filing a petition in OP No. 159/2016-17. The Forum dismissed the petition with a direction that the respondent shall arrange a joint inspection with the petitioner in the premises and expedite the processing of the application for additional load as per Regulation 49 of Kerala Electricity Supply Code, 2014 vide order dated 20-05-2017. Aggrieved against this, the appellant has submitted this appeal petition before this Authority. In this case, it is noted that the appellant is the owner of the High rise building having a LT connection No 9197 and requires additional load, in the extended multi storeyed building having four floors. From the analysis done and the conclusions arrived at I take the following decisions on the reliefs sought above by the appellant. For additional electric load (Power) demanded, the consumer is bound to act as per the Regulations made under Electricity Supply Code, 2014, i.e. under clause 49(4) and 49(5), which requires the installation of an exclusive transformer, in case for a High rise building, irrespective of the load demand. That being a specific rule, the contentions of the appellant does not deserve merit and therefore he is found liable to provide an exclusive transformer for meeting his additional load demand. After obtaining scheme approval from the Electrical Inspectorate and submitting to the respondent, the consumer shall take steps for installing a separate Transformer of suitable capacity and complete other works, for catering the power load for the LT service connections of the High rise building, at his cost. The respondent shall prepare a demand on the estimate cost of work at their end for giving supply to the appellant and serve, at any rate within a period of 7 days from the date of receipt of intimation regarding the scheme approval by the Electrical Inspector and carry out the works on remittance of the estimate cost by the appellant. The respondent shall take proper action to provide the connection without any further delay. Having concluded and decided as above it is ordered accordingly. The order dated 20-05-2017 of CGRF (NR) in OP No. 159/2016-17 is upheld. The Appeal Petition filed by the consumer, Sri. Mambaram Divakaran, is decided as above and stands disposed of. No order on costs.
P/076/2017 Sri Aboobacker P.J. Kozhikode

Download 
Download

M/s Vennakkad Granites is a LT‐IV industrial consumer, under Electrical Section, Koduvally, Kozhikode, having consumer No. 28187. The registered connected load in the premises is 79803 Watts. The consumer is a stone crushing unit registered in the name of Sri. Aboobacker P.J., the appellant. The said service connection was effected on 19-02-2015.The Regional Audit Officer of Kerala State Electricity Board conducted inspection at Electrical Section, Koduvally during the month of November 2016, and noticed an error that the Current Transformer (CT) ratio of the metering circuit is taken as 1 instead of the multiplication factor (MF) 30. On verifying the regular energy bills issued to the consumer, it was found that the bills were issued wrongly taken as MF 1 instead of 30 from 19-02-2015 onwards. Hence a short assessment bill to recover the loss, amounting to Rs. 7,42,715/- was served to the consumer on 09-12-2016. Against this, the consumer had filed a complaint before the CGRF in OP No. 156/2016-17. This was disposed of by allowing 22 monthly equal instalments without any surcharge. Aggrieved by this order, the appellant preferred this appeal before this Authority. From the analysis done and the conclusions arrived at, which are detailed above, I take the following decisions. The order dated 29-04-2017 issued by the CGRF, Kozhikode, in Petition No. 156/2016-17 is upheld. Having concluded and decided as above, it is ordered accordingly. No order on costs.

Contact Us

KERALA ELECTRICITY OMBUDSMAN
D.H. Road & Foreshore Road Junction,
Near Gandhi Square,
Ernakulam, Kerala-682 016
Ph: 0484 2346488, Mob: 8714356488

Any Queries?

Send an email to info@keralaeo.org

Do you Know?

Consumers should submit  petitions to CGRF first before appealing Ombudsman.

Visitors Counter

mod_vvisit_counterToday2483
mod_vvisit_counterAll5351908